DRAFT COPY   DRAFT COPY   DRAFT COPY

MINUTES OF A REGULAR MEETING OF THE

BINGHAMTON-JOHNSON CITY JOINT SEWAGE BOARD

Tuesday, May 9, 2006

City of Binghamton, City Clerk's Conference Room

 

Members Present: Thomas R. Augostini, Chairman

                                    Ronald B. Lake, P.E, Vice-Chairman-ABSENT

                                    Kenneth Kinsman

Thomas Dellapenna, Jr.

                                    Arthur Ospelt

                                    Eugene Hulbert

 

Also Present:          Robert C. Murphy, Esq., Co-Counsel

                                    Kenneth Helisek, Esq., Co-Counsel

                                    William A. Miller, Jr., Superintendent

Catherine P. Aingworth, Assistant Superintendent

                                    Beverly J. Palmer, Fiscal Officer

            Michele Cuevas, Confidential Secretary

            Kathleen C. Carney, Transcriptionist

 

Guests:                     Bob Bennett, Village of Johnson City

                                    Jack Bills, Personnel Services Consultant                        

Gary Holmes, Engineer, City of Binghamton

Brian Kessler, C&S

                                    John LaGorga, Stearns & Wheler

                                    Bob Palladine, C&S

                                    Mayor Matt Ryan, City of Binghamton

Kevin Transue, City of Binghamton Water Department

Bob Weslar, City of Binghamton Councilman

 

                                   

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

 

Chairman Tom Augostini called the meeting to order at 1:34 p.m.  

 

PRIVILEGE OF THE FLOOR

 

Stearns & Wheler

 

John LaGorga presented an update on Stearns & Wheler's projects as follows:

 

Pretreatment & Headworks Analysis:

 

At the last workshop proposed limit changes were discussed for the various industries.  A change has been agreed upon, letters to the various industries are complete and have been mailed.  The Board will have their copies at the June meeting.  They will be meeting with plant management to develop a schedule for permitted deliverable dates.

 

Lime Stabilization Effort:

 

The emergency system is being used on a daily basis, processing approximately 20 tons of sludge per day.  This is a very dusty process and the original intent was to use the process to stabilize inventoried sludge on an emergency basis.  The dust is a concern for Stearns & Wheler as well as plant management.  Mr. LaGorga has been requested by Craig Mattias, the senior operator, to develop a proposal for dust control.  He has prepared a proposal for an interim dust control process.  The cost estimate comes from Aries Chemical.

 

Staffing:

 

Stearns & Wheler is continuing to work on the staffing project and have submitted a draft organization chart with job descriptions.  They are continuing to interview similar type communities to review their overall structure compared to the Binghamton-Johnson City Plant.  There is a meeting scheduled with Superintendent Miller and Assistant Superintendent Aingworth for May 17 to assess the draft organization chart and job descriptions.  They will submit a final draft report at the next Board meeting.

 

Solids Handling Plan:

 

A workshop was held two weeks ago.  Comments from that workshop have been addressed and will be finalized in a letter report. 

 

Lime Stabilization Enhancement Project:

 

Stearns & Wheler has developed a request for proposal and has vendors at the Plant today measuring the truck bay and existing equipment.  They will present shop drawings and proposals for the system.  Those cost estimates are expected within two weeks.  John will present costs and the final schedule for installation and start up at the next Board meeting.

 

Mr. Kinsman asked that the Board review the Lime Stabilization Enhancement Project prior to any work being started.  Stearns & Wheler currently has a written specification for the equipment and a conceptual layout that they have provided to the vendors.  The vendors will provide their proposed plans for installation.  Upon receipt of those plans, Stearns & Wheler will provide them to the Board.

 

Compost Pilot Project:

 

Through the workshop and the solids handling plan, it has been agreed that Stearns & Wheler will provide a proposal to pilot the compost facility.  John LaGorga has a proposal for that today.  Their original plan was to provide a proposal "from A to Z" to present today to the Board.  They have had some compost experts at the Plant for investigation and feel the best way to approach this project is in steps.  The proposal today is for the up front work plan.  They would like to provide the Board/Plant with a work plan laying out the operation settings, a current schedule and set of costs.  They are not ready to provide this information without doing the work plan first.

 

Mr. LaGorga will provide the Board with a proposal for the work plan (today).  The proposal proposes that the work plan be completed by the July Board meeting.

 

Mr. Kinsman explained that this study would be of one reactor, operating and studying the reactor and making a prediction of whether the compost facility is worth operating. 

 

Mr. LaGorga reported that Stearns & Wheler has a tour planned at the Syracuse Metro Treatment Plant for the BAF facility there on May 22, 2006.  Stearns & Wheler will come to the Plant with a bus, pick up Board members and Plant personnel and travel to Syracuse for the tour.  This tour will allow for peer-to-peer discussions.

 

Mr. Hulbert asked (of Stearns & Wheler) for a list of the uses of the Syracuse plant compared to the uses of the Binghamton plant.  John LaGorga will provide that information on the day of the tour.

 

John distributed two amendments, one for the interim solids handlings and one for the dust control.

 

Mr. LaGorga explained the dust control process:  The lime hopper has a cover, which is removed when lime is added (4 or 5 bags at a time).  Once the hopper is filled, the cover should be replaced.  In order to monitor what is happening, the cover will be taken (and kept) off.   The hopper also gives off dust during operation.

 

Mr. Hulbert asked how much the dust would be reduced by using the dust control process.  Mr. LaGorga explained he could not give a quantitative number, but that it would be a significant reduction in the dust.

 

Assistant Superintendent Aingworth reported that a PERMA representative visited the site to evaluate the safety procedures being utilized in lime stabilization.  He is scheduling a visit with an industrial hygienist to measure the dust and its implications.  The PERMA representative watched the loading and the process and advised of some remedial steps to help alleviate the dust situation.  All employees working with lime stabilization are wearing the breathing apparatus, suits, etc.   The PERMA representative felt that the safety procedures that have been implemented are more than adequate.  An official report will be submitted after the industrial hygienist visits the Plant.

 

Mr. Murphy advised that PESH would provide helpful insight and advice.  Mr. Augostini advised implementing the recommendations from PERMA before inviting PESH in for a review. 

 

Mr. Hulbert asked for an explanation of the goals and procedures that will come from the compost facility pilot.

 

Mr. LaGorga explained that an actual design will be formulated from this work plan.  They have had their compost experts visit and review the compost facility.  They have come back with several operational settings that could be piloted.  By doing the work plan, they should be able to provide a dollar figure of what it would cost to pilot the compost facility. 

 

Chairman Augostini asked for a motion to approve Amendment #7 (Compost Pilot Program).

 

Mr. Hulbert made a motion to approve Amendment #7 to the agreement with Stearns & Wheler.  Second by Mr. Ospelt.

 

Mr. Hulbert amended the motion as follows:  The motion includes that this is part of a professional services contract which exempts bidding.  The other reasons for it not being bid are the same reasons set forth at the Board Meeting on April 11, 2006 and the resolution adopted at that time setting forth that these are emergency measures, the possible fines and the same reasoning for the adoption of this amendment will apply to the previous amendment adopted on April 11, 2006 for the same reasons set forth therein.  This motion also authorizes the chairman to sign the amendment with funds to come from the capital reserve. 

Second by Mr. Ospelt. 

 

Motion carried:       4 ayes

                                                1 nay

                                                1 abstain

 

Chairman Augostini asked for a motion to approve Amendment #8 (dust control process).  

 

 

Mr. Ospelt made a motion to approve Amendment #8.  This is part of a professional services contract which exempts bidding.  The other reasons for it not being bid are the same reasons set forth at the Board Meeting on April 11, 2006 and the resolution adopted at that time setting forth that these are emergency measures, the possible fines and the same reasoning for the adoption of this amendment will apply to the previous amendment adopted on April 11, 2006 for the same reasons set forth therein.  This motion also authorizes the chairman to sign the amendment with funds to come from the capital reserve. 

Second by Mr. Hulbert. 

 

Motion carried:       4 ayes

                                                1 nay

                                                1 abstain

 

C&S

 

Dye Testing

 

Bob Palladine presented the Board with photos and results from the dye testing done on the clarifiers at the Plant and explained the results of the initial testing. 

 

SPEDES Permit

 

The formal list of comments has been completed and reviewed by co‑counsel Bob Murphy.  They have communicated with DEC and they are willing to review these informally.  Steve Eidt has informed Bob Palladine that he has reviewed the comments and is amenable to some changes. 

 

Mr. Murphy suggested meeting with Steve Eike in Syracuse to discuss the comments.  There will be a meeting scheduled to discuss these comments within the next two weeks. 

 

Bob Palladine reported that for the final permit they are asking for more reasonable nitrogen limits and mercury limits. 

 

He also reported that both owners' names will be included on the SPEDES permit.

 

Treatment Unit Monitoring Work Plan

 

At the April meeting the Board had asked for a proposal for a monitoring work plan to perform testing of all units once the Plant is up and running.

 

The Plant will prepare an initial sampling plan. 

 

Bob Palladine presented the Board with letter of authorization #3 for a time and materials contract for $2,082.00 to complete this work. 

 

This work is required to be completed three months prior to start up.  Currently the schedule calls for the filling of tanks and producing a biomass on August 15, 2006. The testing to actually run the process is scheduled for September 15, 2006.  This is when the sampling would need to begin. Three months prior to September 15, 2006 is June 15, 2006; three months prior to the tanks being filled is May 15, 2006.  Bob Palladine has communicated with Steve Eike that June 15, 2006 would be a more reasonable date.  Assistant Superintendent Aingworth has begun work on the sampling plan and will submit an outline to the DEC by May 15, 2006. 

 

Mr. Hulbert made a motion to approve work plan #3.  Second by Mr. Ospelt.

 

Motion carried:       5 ayes

0 nay

1 absent 

 

Influent Bar Screens

 

Bob discussed the issue of rags and clumps getting through the screens and it was suggested that the Plant look at closer spacing of the influent bar screens.  He reported that the screens used by the Plant are IDI screens, standard in the industry.  They are currently 3/4" spacing.  C&S and IDI both suggest using a screen with 1/2" spacing.  Superintendent Miller will meet with Bob Palladine and submit a recommendation for screens with a schedule for implementation via e‑mail to Chairman Augostini.

 

March 29, 2006 Process Meeting

 

Bob Palladine distributed to the Board a summary from the March 29,2006 process meeting between Stearns & Wheler, C&S and Black & Veatch.

 

Mr. Kinsman reported that Frank Regala will be in town on Friday, May 19, 2006 for a meeting in Johnson City at 9:00 a.m.

 

Mr. Kinsman has informed all parties of the meeting.  This meeting is to discuss potential problems and solutions.

 

GARY HOLMES, CITY ENGINEER

 

Mr. Holmes advised that it was a good idea to bring people in to talk about the new system as some things may come up on the operational level.  At this point, it is late in the process to look at changes in the design.  He is fairly confident that based on the design they will get the desired results. 

 

BOB BENNETT, VILLAGE ENGINEER

 

Mr. Bennett reminded the Plant/Board that IDI will be on staff running the Plant for 18 months and instructing the Plant staff on how to run it. 

 

Contract 2

 

The bonding company's option at this point in time is "out the window".  They have begun the process of preparing bids to secure an outside contractor to fix the pumps.  It is hoped to have a new contractor on board by the end of May.

 

Contract 3

 

Contract 3 is approximately 90% complete.  The media is in Albany, there has been coordination meetings regarding the media.  The air process needs to be connected before the media can be installed. 

 

Contract 4

 

The solids handling contract is approximately 70-75% complete and is on schedule to be completed by September 2006.

 

Mr. Helisek referenced a letter from Gary Holmes dated April 17, 2006 regarding the rejection of the bid for railings around the settling tanks.  He asked Mr. Bennett for his response to this letter. Mr. Bennett agreed with Mr. Holmes' recommendation that the bid should be rejected until the BAF system is in place.  After the BAF system is installed, the railings will be re-bid.

 

APPROVAL OF MINUTES

 

Chairman Augostini asked for a motion to approve the minutes from April 11, 2006.

 

Mr. Hulbert indicated that "February" on Page 11 (Superintendent's Report) be changed to "March".

 

Mr. Ospelt made a motion to accept the minutes from April 11, 2006 as amended.  Second by Mr. Dellapenna.

 

Motion carried:       5 ayes

0 nay

1 absent 

 

FISCAL OFFICER'S REPORT

 

Ms. Palmer presented a Fiscal Officer's report totaling 2,762,907.74 as of May 8, 2006. 

 

Chairman Augostini asked for a motion to accept the Fiscal Officer's report. 

 

Mr. Hulbert asked for a map of the service area.  Mr. Kinsman will provide a service area map to Mr. Hulbert.

 

Mr. Kinsman made a motion to accept the Fiscal Officer's report as presented.  Second by Mr. Hulbert. 

 

Motion carried:       5 ayes

0 nay

1 absent 

 

BOARD LISTING

 

Ms. Palmer presented a Board Listings totaling $274,996.46. 

 

Mr. Hulbert made a motion to approve and pay the Board Listing as presented.   Second by Mr. Ospelt.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Ms. Palmer pointed Board members' attention copies of the budget.  The current budget ends May 8, 2006 (on the capital page) does not contain the amount that was brought forward from 2005.  She will bring that forward for the June meeting.  There is currently $1.7 million in capital (not $750,000.00).

 

Mr. Kinsman asked Ms. Palmer if she had the break out information for the ongoing projects.  She will have that information for the June meeting.

 

 

SUPERINTENDENT'S REPORT

 

Violations, Complaints & Significant Problems

                                   

·        There were no odor complaints or violations received this month. 

 

Personnel

 

·           Management personnel continue management training with consultant Jack Bills.

·           Another mechanic has retired as of April 28, 2006.

·           Interviews for Building Maintenance Helper are being conducted.

 

Compost Facility

 

·           Additional compost facility temporary repairs need to be undertaken.  As directed in the previous meeting, we are working on bid specifications with Stearns and Wheler for additional repairs of the compost facility.

·           We are removing the biosolids from the compost reactors in preparation for repairs.

·           We have received a report from the EPA indicating that a quality audit was performed on the contract lab that performed compost analysis for us, and numerous deficiencies were found.  We will no longer be contracting with this lab to perform analysis for us.  Currently all biosolids are disposed of at the landfill.  We must respond to the EPA within 45 days regarding this matter. 

·           Sawdust will be bought on an as needed basis.

 

Operations

·        The effluent suspended solids limit was met in April, with great improvement in percent removal.  Plant personnel are working diligently to remove solids inventory in the plant, operating the centrifuge 6 days per week and removing an average of 90 tons of solids per week.  

·        Influent suspended solids were 175, and effluent suspended solids were 36, which is an average 79% removal.  Current effluent limits for Suspended Solids are 53.  Influent BOD was 182 and effluent BOD was 107, which is an average 41% removal.  The effluent BOD limit is 132.

·        Iron limits were met in 8 out of 8 samples.  High iron contained in the centrate and effluent continues to be an issue we monitor closely.

·        There were no settleable solids violations.  Plant personnel are working to evaluate performance strategies to optimize the process.

·        Plant personnel met with Stearns & Wheler to assist in the design for lime stabilization.

·        Plant personnel met with a representative of PERMA regarding employee health and wellness as it relates to the lime stabilization operation.

·        Plant personnel met with C&S to review design options for chlorination and dechlorination.

·        Plant personnel assisted C&S with detention time flows in settling tanks.

·        Assistant Superintendent Aingworth toured the Roanoke Wastewater Treatment Plant to learn about their experience with BAF issues, as well as to discuss management and training topics at their facility.

·        Oxy-Pro has agreed to send a limited supply of the product for testing in the centrifuge centrate return stream.

 

Digesters

 

·              Number 3 digester is working to meet the stabilization requirements.  We continue to analyze solids data in order to balance digestion requirements, composting and lime stabilization operations. 

 

Centrifuges

 

·              The Westphalia centrifuge is on-line and working very well.  The two new centrifuges are scheduled to be on line within two months.

 

Influent Pumps

 

·              Corrective action is being planned through C & S Engineers and lead agency, the Village of Johnson City.  There was an independent evaluation performed and the report is pending.

   

 Primary Tanks

 

We are in Primary only mode.   We are working with C&S in an effort to determine the short-circuiting and flow patterns of the tanks using dye testing.

 

Industrial Pretreatment Program

 

·        Stearns & Wheler is assisting our staff with the Industrial Pretreatment Program. 

·        Gavin Vitale, our plant lab technician, attended a four-day Industrial Pretreatment Course in order to assist with the Industrial Pretreatment Program at the plant.

 

Plant Business

 

·        We are exploring and gathering information from several companies regarding an asset management plan.  We have recorded a large portion of the plant equipment and are working with contractors to itemize and record new equipment to enter into our database. 

·        State Contract Bids have been completed for the purchase of a new truck to assist in the removal of solids.  Our main option for solids removal has been Bert Adams.  We would like to purchase a truck to remove the solids in a more efficient manner.  This would equate to less down time for the centrifuges by eliminating the need to call for a driver and the time to switch the cans out.  The total State Bid price is $112,995.81.  The truck is the same brand and size of our other truck.  Bert Adams will still remain as a standby method of solids removal.  This was discussed in the October, November and December meetings and determined to be the best method for removing solids from the plant.

 

Mr. Ospelt asked that a synopsis of all trucks available on State Contract be provided detailing the truck, price and company bid results.  Superintendent Miller to provide this information at the June meeting.

 

Recommended Board Actions

 

·        Approval to purchase a truck on State Contract.

 

Contract 3 – BAF's

 

Work is in progress with 87% of the time allotment used with 92% of the work completed or in progress.  This does not include the five-week extension that may be granted by the DEC.

 

Contract 4 – Solids Handling

 

Work is in progress with 75% of the time allotment used with 75% of the work completed or in progress. 

 

NEW BUSINESS

 

Chairman Augostini discussed an e-mail received from We Care Organics for sludge hauling at $63.00/ton.   The Board discussed using We Care on an as needed basis as an alternative to disposing of sludge.  Superintendent Miller will provide more information at the June meeting.

 

Assistant Superintendent Aingworth discussed with the Board the elevated loadings that are entering the Plant.  Superintendent Miller will investigate this issue further.

 

Assistant Superintendent Aingworth also reported that the Plant is not using Eastern Laboratories any longer.

 

Mr. Kinsman expressed concern regarding the issue that the County is going to contract with Stearns & Wheler to make a determination about the Plant.  As the Board/Plant is currently employing Stearns & Wheler, he feels there is a conflict of interest.

 

Mr. Helisek will send a letter to the County informing them that Stearns & Wheler is under contract with the Plant now and that the Board would consider it inappropriate for the County to contract with them regarding the Joint Sewage Board.

 

Mr. Kinsman made a motion to authorize co-counsel Mr. Helisek to forward a letter to the Broome County attorney stating that Stearns & Wheler is under contract with the Joint Sewage Board and any potential contract that the County has with Stearns & Wheler regarding the Joint Sewage Board would be a conflict of interest.  Second by Mr. Dellapenna.

 

Motion carried:       4 ayes

0 nay

2 absent

 

Mr. Kinsman made a motion to hereby move to authorize the Board to settle the present pending litigation by the United States Environmental Protection Agency, Region 2, against the Binghamton Johnson City Joint Sewage Treatment Facility, Docket Number CWA-02-02006-332, which alleges violations of timely reporting of annual sludge reports and to accept the offer of settlement set forth on the reverse side of the US EPA's correspondence dated May 2, 2006 to pay a penalty of $1,100.00 in accordance with the terms of the CA/OF.  Further moving to authorize the chairman of the Joint Sewage Board to enter into the consent agreement in said correspondence in full settlement of all charges and move that the payment of the fine be made from J8130.4510 (permits/fines) payable to the Treasurer of the United States of America and that said compromise be forwarded forthwith to the US EPA together with the executed consent agreement and final order.   Second by Mr. Dellapenna.

 

Motion carried:       4 ayes

0 nay

2 absent

 

Mr. Dellapenna made a motion to authorize attorney Murphy to contact the EPA in response to the follow up performance inspection of Eastern Laboratory Services, notifying them of the Plant's termination of Eastern Laboratory Services, intention to prepare an RFQ for new laboratory services and asking for their recommendation of any laboratory services that they have inspected recently.  Second by Mr. Hulbert.

 

Motion carried:       4 ayes

0 nay

2 absent

 

OLD BUSINESS

 

Mr. Murphy will provide disclaimer language allowing Binghamton University students to conduct research at the Plant.

 

EXECUTIVE SESSION

 

Mr. Dellapenna made a motion to enter Executive Session at 3:08 p.m. for the purpose of discussing personnel issues and possible litigation issues.  Second by Mr. Ospelt.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Mr. Dellapenna made a motion to exit Executive Session at 4:54 p.m.  Second by Mr. Hulbert.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Mr. Dellapenna made a motion to adjourn.  Second by Mr. Hulbert. 

 

Motion carried:       4 ayes

0 nay

2 absent

 

Meeting adjourned at 5:22 p.m. 

 

Motion by Mr. Kinsman to reconvene the meeting at 5:23 p.m.  Second by Mr. Dellapenna. 

 

Motion carried:       4 ayes

0 nay

2 absent

 

Motion by Mr. Kinsman to allow two people to attend the NYWEA conference on June 5-8 and pay all customary expenses.  Second by Mr. Dellapenna.

 

Motion carried:       4 ayes

0 nay

2 absent

 

Motion by Mr. Dellapenna to adjourn the meeting at 5:27p.m.  Second by Mr. Kinsman. 

 

Motion carried:       4 ayes

0 nay

2 absent

 

The next regularly scheduled meeting is scheduled for Tuesday, June 13, 2006 at 1:30 p.m. at the Village of Johnson City, Second Floor Conference Room.


 

 

 

TIME & PLACE OF NEXT BOARD MEETING

 

 

Tuesday, June 13, 2006 @1:30 PM

Village of Johnson City, 2nd Floor Conference Room

 

 

Respectfully submitted,

 

 

Kathleen C. Carney

Transcriptionist

 

 

 

 

 

 

 

 

cc:       All Board Members

            Mayor Ryan, City of Binghamton

            Mayor Lewis, Village of Johnson City

            Kenneth P. Helisek, Esq.

            Robert C. Murphy, Esq.

            Beverly J. Palmer, Fiscal Officer

            William A. Miller, Jr., Superintendent

            City of Binghamton, City Clerk

Haylor, Freyer & Coon

File