DRAFT COPY   DRAFT COPY   DRAFT COPY

MINUTES OF A REGULAR MEETING OF THE

BINGHAMTON-JOHNSON CITY JOINT SEWAGE BOARD

Thursday, July 11, 2006

City of Binghamton City Clerk's Conference Room

 

Members Present: Thomas R. Augostini, Chairman

                                    Thomas Dellapenna, Jr. -- ABSENT

                                    Eugene Hulbert

                                    Kenneth Kinsman

                                    Arthur Ospelt

Kevin Transue

 

Also Present:          Robert C. Murphy, Esq., Co-Counsel

                                    Kenneth Helisek, Esq., Co-Counsel

                                 Catherine P. Aingworth, Acting Superintendent

                                    Beverly J. Palmer, Fiscal Officer

            Michele Cuevas, Confidential Secretary

            Kathleen C. Carney, Transcriptionist

 

Guests:         Mayor Matt Ryan, City of Binghamton

Bob Bennett, Engineer, Village of Johnson City

Howard LaFever, Stearns & Wheler

                                    John LaGorga, Stearns & Wheler

                                    Art Van Gelder, C&S Engineers

                                    Bob Palladine, C&S Engineers

                                    Brian Kessler, C&S Engineers

                                    Jack Bills

                                   

                                                                       

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

 

Chairman Tom Augostini called the meeting to order at 1:39 p.m.

 

 

 

PRIVILEGE OF THE FLOOR

 

C&S Engineers

 

Art Van Gelder provided an update on the improvements as related to the flood events.  He provided aerial photos taken during the flooding.  C&S met with the insurance carriers for the builder's risk policies on July 11, 2006 and gave a tour of the new construction projects.  Contracts 1, 3 and 4 are affected by the flooding.  C&S is estimating the flooding will cost a schedule setback to the construction projects of 6-12 months.  They do not know how long it will take to get equipment back from manufacturers.

 

Under Contract 4, 70% of the pumps and grinders are going back to the manufacturers.  All piping must be discontinued before pumps can be taken out.  There are 57 valves that will be disconnected. 

 

Under Contract 3, Square D is the predominant electrical vendor.  Any motor controllers, starters or disconnects that came in contact with the slightest amount of water must be removed and sent back to them.  All the pneumatic valves were under water.

 

The pit has been dewatered and cleaning efforts are under way.  The new sump pumps under Contract 3 have all been replaced.  C&S is working diligently to get as much of the silt as possible out of the system and out of the building. 

 

C&S' engineers have visited the site to evaluate everything from architectural to structural and mechanical systems.  Rooms that had just been painted will need to be repainted.  

 

All contracts are continuing to progress where possible.  The contractors are assisting the plant staff where they need help and ask for assistance. 

 

Mr. Palladine reported that structural, mechanical and electrical engineers conducted a field visit to the plant.   Reports from the special teams are due by the end of this week (week of July 10, 2006). 

 

Mr. Palladine presented Letter of Authorization #4 to Chairman Augostini.  He explained that work related to Contracts 3 and 4 is being handled under those contracts.  Clean up/repair work for the existing plant will be handled at the Board's request.  He reviewed the conditions of Letter of Authorization #4 with the Board.

 

He reported that FEMA and the DEC are visiting the plant on July 12, 2006.  The DEC has asked about cost and schedule.

 

Mr. Helisek asked, in reference to Letter of Authorization #4, if it would be in a format that could be used as a claim for insurance purposes.  Mr. Palladine indicated it would be.  Mr. Palladine will provide a not to exceed cost for rates. 

 

Chairman Augostini informed the Board that Steve Eidt (DEC) requested that the Board secure an engineering study to assess flood damage to the existing Plant.

 

Mr. Van Gelder supplied the Plant's insurance agent with an inventory (to date) from all contractors.  The insurance company will want a more detailed breakdown as well as a more definitive cost and time schedule.  Each contractor has been asked to make an assessment and provide that to the construction management team.  C&S will review all of these assessments with the Board in order to develop a plan. 

 

Chairman Augostini directed that all costs should be delineated as to the project damage (those under construction) and non-project (existing plant). 

 

Mr. Hulbert asked C&S if this information could be provided in web format for easy access by all Board members, Plant management, etc.  Mr. Palladine will create a separate FTP site where he will post information and correspondence relative to the flood and insurance claims.  He will provide passwords for the FTP site. 

 

Mr. Van Gelder reported that they are continuing to install filter media into the end cells (when they can get the media due to the washout on Route 88).  They are progressing with welding on the C-cells that are above the damage water line.  Once they are done with the stainless steel piping, they will begin loading media into the C-cells as well.  There is some contract electrical work being conducted above the damage water line.  Contract 4 is predominantly damage assessment and damage repair.  They are being able to progress work on a limited basis on Contract 3.  Half of Faulter's crew is performing progressing work versus clean up and repair. 

 

Mr. Van Gelder reported that the stockpiled media stored at the Village of Johnson is a concern only as to the proximity of the salt pile.  They do not feel that it is a major concern at this point, as they will waste the bottom 1-2 inches of the pile.  They have been performing random sampling of the salt pile and have not found any trace petroleum, grease or solvents. 

 

IDI has advised C&S that silt in the media is not a problem and it will come out rather easily during the backwash operations of the pump filters.  IDI has expressed no concern regarding the silt.  IDI's position regarding the silt has been documented. 

 

Mr. Hulbert asked that a visible inspection be done to determine how much silt had settled in the bottom of the tank.   Mr. Transue suggested scoping the filter media at 12‑inch intervals to see where the silt had infiltrated. 

 

Mr. Hulbert asked about open valves which caused a backwash problem.  Mr. Van Gelder responded that IDI has a problem with some of their pneumatic valves, which caused the backwash problem.  Mr. Hulbert asked that a complete reporting and  documentation be performed on what caused the flooding of the tanks, in order to prevent such severe damage in the future. 

 

Mr. Van Gelder explained that valves associated with N1 and N5 are not seating properly and cannot be seated.  IDI was in the process of bringing the manufacturer to the site specifically for these valves.  The valves were closed, but will not seat properly (not even manually).  He will supply Acting Superintendent Aingworth with a complete report on the valves.

 

Mayor Matt Ryan

 

Mayor Ryan asked if a request had been made to the DEC for an extension.  Chairman Augostini replied that the DEC was visiting the plant on July 12, 2006 (along with FEMA) and had requested an engineering study be done of the damage/schedule/costs.

 

Mayor Ryan asked to be kept apprised of any telephone calls that need to be made regarding an extension request.

 

The Mayor asked what the status was of insurance coverage for the Plant by contractors and by the Plant.  Chairman Augostini explained that related to the construction the Plant has two policies – Contract 3 and Contract 4 each have a one million dollar builder's risk policy.  These policies include repair specific to these two contracts.

 

The Plant has never had flood insurance.  FEMA never advised the Plant that flood insurance was required after providing aid for the flood of 2005. 

 

Mayor Ryan asked how much of the Plant was operational.  Acting Superintendent Aingworth responded that three settling tanks were brought online but one has crashed.  They believe they will get three more back online on July 12.    As they bring processes online, the silt is so heavy that it is ripping things apart.  They are waiting for supplies and visits by manufacturers representatives. 

 

Mayor Ryan asked about the mercury limits for dental labs/offices.  Mr. Palladine responded that the new permit has a limit for mercury and all new labs and offices will be required to stay within these limits. 

 

Attorney Murphy added that there is correspondence being sent to the County Planning Department in order to notify the towns of the new mercury limits. 

 

Acting Superintendent Aingworth indicated the Plant is taking 16.3% from Binghamton and 4% from Johnson City. 

 

C&S Engineers – Bob Palladine

 

 

 

Mr. Palladine reported that the DEC is modifying the permit, but has not reviewed it in the last two weeks.  They are currently about one-third of the way through it.  He will provide notice of the schedule for the modified permit.

 

Improvements to the clarifiers and baffles had been discussed as a change order under Contract 3.  This work is underway.  He has prepared a scope for the change order.  Mr. Palladine distributed photos of the tanks and baffles to the Board and explained the proposed changes. 

 

Mr. Palladine estimated that the tanks would work at 65% efficiency (they work at 50% currently) after the improvements are made. 

 

Chairman Augostini asked for a motion to approve Letter of Authorization #4 with C&S Engineers related to the flood damage assessment report for damage related to the day-to-day operations at the Plant.  The new construction will be assessed out of the budget for new construction. 

 

Mr. Kinsman made a motion to  approve Letter of Authorization #4 with C&S Engineers related to the flood damage assessment report to include detailed rate charges clarified.  Second by Mr. Hulbert. 


Mr. Hulbert asked for a detailed flood damage recommendation analysis (in the event of a future flood).  Mr. Transue asked for a monthly report on hours from C&S.  Mr. Palladine will provide a not to exceed rate schedule.

 

Motion carried:       5 ayes

0 nay

1 absent

 

(Mayor Ryan thanked everyone for their efforts prior to exiting the meeting at 2:30 p.m.)

 

Bob Bennett

 

Bob reported that the Village Attorney, Art Van Gelder's staff and himself have a meeting on July 13, 2006 to discuss the pump issues from Contract 2. 

 

Stearns & Wheler:

 

Lime Stabilization

 

John LaGorga provided layout options and configurations for raised conveyers as requested by Mr. Hulbert at the June 29, 2006 meeting.  He explained the various configurations, recommending either configuration D or E.  They are currently working with the manufacturers to fine tune these configurations.  He does not have a final cost at this point, but will continue to work with the manufacturer to develop a cost. 

 

Mr. LaGorga provided Amendment #9 which is a total of $350,250.00 plus $220,000.00 (original Amendment #6) for Lime Stabilization.

 

Mr. Hulbert asked if all members agree to decommissioning the compost facility to be replaced by lime stabilization.  Chairman Augostini reminded the Board that Sandy Lizlovs had communicated to Howard LaFever that she did not have a preference to which two forms of pretreatment were used, as long as there were two forms.  Mr. LaFever indicated they are still waiting for that directive in writing from the DEC.

 

Attorney Murphy recommended that the Board not make any motions decommissioning the compost facility until approval from the DEC/EPA  with regards to decommissioning the compost facility is received. 

 

Chairman Augostini asked for a motion to approve Amendment #9 with Stearns & Wheler.

 

Mr. Kinsman made a motion to approve Amendment #9 establishing a lime stabilization operation and equipment as supplied by Stearns & Wheler with funds coming from the capital reserve.  Second by Mr. Hulbert.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Staffing Project

 

Mr. LaGorga reported that he has met with Attorney Murphy and Mr. Bills to further this project.  They would like to finalize the project and possibly have another workshop within the next two weeks with the Board to finalize the project.

 

Industrial Pre-Treatment Program

 

Mr. LaGorga indicated that Amendment 2006 has been submitted to carry on with the Pre-Treatment Program until March 31, 2007.  Amendment 2006 includes a $10,000.00 one-time increase due to the increased reporting due this year and also contains the standard conditions. 

 

Mr. Hulbert reiterated his request for a list of all filings and reporting to the various agencies.  Mr. LaGorga indicated they will produce a compliance calendar. 

 

Chairman Augostini also asked for a procedure of how to proceed with an agreement with Broome County to exchange sludge for leachate.  Attorney Murphy sent a letter to Broome County Executive Fiala inviting a representative to attend the next meeting in order to begin a conversation regarding coordinating these efforts. 

 

Chairman Augostini asked for a motion to approve Amendment Year 2006 of the Industrial Pre-Treatment Program. 

 

Motion made by Mr. Hulbert approving Amendment Year 2006 of the Industrial Pre‑Treatment Program.  Second by Mr. Ospelt.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Jack Bills, Personnel Consultant

 

Mr. Bills reported that he has put together a manning table and an organization chart.  He is still a believer in the functional organization chart and stands by the organization chart he submitted with his report, with the exception of some job titles that were submitted.  He will submit the manning table next week with his recommendations. 

 

Chairman Augostini asked that the organization be broken down by shift.

 

Mr. Kinsman felt that Assistant Superintendent Aingworth should be allowed to make a recommendation as to which organization to adopt after reviewing both.

 

APPROVAL OF MINUTES

 

Chairman Augostini asked for a motion to approve the minutes from June 13, 2006.

 

Mr. Ospelt made a motion to accept the minutes from June 13, 2006 as presented.  Second by Mr. Kinsman.

 

Motion carried:       5 ayes

0 nay

1 absent 

 

Chairman Augostini asked for a motion to approve the minutes from June 29, 2006.

 

Mr. Kinsman made a motion to accept the minutes from June 29, 2006 as presented.  Second by Mr. Transue.

 

Motion carried:       4 ayes

0 nay

1 absent 

1 abstention

 

FISCAL OFFICER'S REPORT

 

Ms. Palmer presented a Fiscal Officer's report totaling 2,698,395.81.  All third quarter billings were mailed.

 

Ms. Palmer presented to Board members the listing of current encumbrances for outstanding projects.  She will update them for the next meeting.

 

Chairman Augostini asked for a motion to accept the Fiscal Officer's report. 

 

Mr. Ospelt made a motion to accept the Fiscal Officer's report as presented.  Second by Mr. Kinsman. 

 

Motion carried:       5 ayes

0 nay

1 absent 

 

BOARD LISTING

 

Ms. Palmer presented a Board Listings totaling $277,537.82. 

 

Mr. Hulbert made a motion to approve and pay the Board Listing as presented.   Second by Mr. Ospelt.

 

Motion carried:       5 ayes

0 nay

1 absent

 

SUPERINTENDENT'S REPORT

 

Violations, Complaints & Significant Problems

                                   

·        The plant has been severely damaged by the flood of June 28.  DEC engineers, as well as structural, mechanical and electrical engineers from C&S have toured the facility to assess damages.  FEMA, SEMA and insurance adjusters are expected to evaluate the facility this week.

·        Damage was to equipment including valves, pumps, motors, meters, grinders, VFDs, in the thickeners, east and west settling tanks, air scrubbers, digesters, chlorination and dechlorination building as well as the new BAF area.

·        Significant damage was sustained at the Johnson City Terminal Pump Station.

·        The Binghamton Sample Building was destroyed by the flooding.

 

Compliance

 

·           The effluent suspended solids limit was met in June.  Data was not available after June 27, 2006.

·           Influent suspended solids were 142, and effluent suspended solids were 33, which is an average 76% removal.  Current effluent limits for suspended solids are 53.  Influent BOD was 171 and effluent BOD was 103, which is an average 40% removal.  The effluent BOD limit is 132.

·           Iron limits were met in all samples collected.

·           Sampling was discontinued after the flooding.

 

Personnel

 

·           Completed:  One Building Maintenance Helper has been hired. 

·           Pending:  We are coordinating with Binghamton Civil Service to review qualifications for several positions including shift operator, computer analyst (approved and funded as of June 1), as well as instrumentation technician. 

·           Continuing: Management personnel continue management training with consultant Jack Bills.

 

Compost Facility

 

·        Continuing:  We are working on bid specifications with Stearns & Wheler for additional repairs of the compost facility.

·        Continuing:  We continue to have discussion with the EPA regarding our 2005 biosolids report.  We have responded with additional information that they have requested. 

 

Operational Issues

 

·           Flooding on June 28 has seriously impacted operations of the plant.

·           Plant personnel are working overtime in their efforts to bring the plant back to pre‑flood conditions.

·           Plant personnel have received quotes for the replacement of our skimming system.  The current skim troughs are leaking profusely, and result in continuous pump operation and grease problems.

·           Plant personnel have received price information regarding replacement of the bar screens.

·           Plant personnel continue to meet with Stearns & Wheler to assist in the design for lime stabilization.

 

Digesters

 

·              Number 3 digester is currently dormant due to damage to equipment. 

 

Centrifuges

 

·              The Westphalia centrifuge is on-line.  The two new centrifuges are scheduled to be on line within two months.

 

Influent Pumps

 

·              Pending:  Corrective action is being planned through C & S Engineers and lead agency, the Village of Johnson City.  The Johnson City Terminal Pump Station suffered significant damage.  The corrective action being coordinated by Johnson City may assist in the repair of some problems. 

   

 Primary Tanks

 

We are in Primary only mode with tanks 1 and 2 on line.  Currently 5 out of 10 tanks are functioning.

 

Industrial Pretreatment Program

 

·        Continuing:  Stearns & Wheler is assisting our staff with the Industrial Pretreatment Program. 

 

Contract 3 – BAF's

 

Work is in progress but has suffered a significant setback with the flooding of June 28, 2006.

 

Contract 4 – Solids Handling

 

Work is in progress but has suffered a significant setback with the flooding of June 28, 2006.

 

Mr. Ospelt commended Acting Superintendent Aingworth for the job she has performed at the plant since the flooding. 

 

Acting Superintendent Aingworth added that the plant staff has been phenomenal in stepping up and working overtime.  Many people have cancelled vacations and have been working 12-16 hour days. 

 

Motion by Mr. Ospelt to provide breakfast pizzas to thank the staff from the Board.  The pizzas will be provided on July 12, 2006.  Second by Mr. Kinsman.  (Funds were collected from Board members).

 

Motion carried:       5 ayes

0 nay

1 absent

 

CORRESPONDENCE

 

Assistant Superintendent Aingworth indicated a letter from Mayor Ryan regarding Mr. Lake's appointment. 

 

Attorney Helisek reported he has heard nothing from the Department of Health regarding restaurant inspections (grease issues) pursuant to the letter he sent to the Department of Health.

 

Attorney Helisek reported that he sent a letter dated June 29, 2006 to the EPA enclosing the check for fines in the amount of $1,100.00 along with the consent order.  He has received a certified mail receipt.

 

BOARD COMMITTEE REPORTS

 

Mr. Kinsman reported that the Personnel Committee met with Mr. Bills regarding the salary projections and they are continuing to develop salary ranges for non-union employees.  They will come up with a salary range for the shift supervisor (newly developed) position. 

 

OLD BUSINESS

 

Ms. Palmer indicated that the budget will be due early this year.  The Board informed Ms. Palmer that Mr. Miller will be responsible for compiling the budget as one of his projects.

 

NEW BUSINESS

 

Mr. Hulbert indicated he would like to make sure that the Board gets started with the municipal working orders regarding how the owners should be approached with regard to 239 l and m procedures and requesting sewage services for new developments. 

 

Attorney Murphy indicated he has written to Rita Petkash on this issue. 

 

Mr. Hulbert would like to see a procedure developed for these new requests.

 

EXECUTIVE SESSION

 

Motion by Mr. Kinsman to enter Executive Session at 3:45 p.m. to discuss personnel issues.  Second by Mr.  Hulbert.

 

Motion carried:       5 ayes

0 nay

1 absent

 

Motion by ________ to exit Executive Session at _____ p.m.  Second by __________. 

 

Motion carried:       5 ayes

0 nay

1 absent

 

 

 

Motion by _____________ to adjourn at _____ p.m.  Second by ________.

 

Motion carried:       5 ayes

0 nay

1 absent

 

The next regularly scheduled meeting is scheduled for Tuesday, July 25, 2006 at 1:30 p.m. in the Second Floor Conference Room in Johnson City.  The first August meeting will be Tuesday, August 11, 2006 at 1:30 p.m. in the Second Floor Conference Room in Johnson City.


 

 

 

TIME & PLACE OF NEXT BOARD MEETING

 

 

Tuesday, July 25, 2006 @1:30 PM

Johnson City, Second Floor Conference Room

 

 

Respectfully submitted,

 

 

Kathleen C. Carney

Transcriptionist

 

 

 

 

 

 

 

 

cc:       All Board Members

            Mayor Ryan, City of Binghamton

            Mayor Lewis, Village of Johnson City

            Kenneth P. Helisek, Esq.

            Robert C. Murphy, Esq.

            Beverly J. Palmer, Fiscal Officer

            Catherine Aingworth, Acting Superintendent

            City of Binghamton, City Clerk

Haylor, Freyer & Coon

File