DRAFT COPY   DRAFT COPY   DRAFT COPY

MINUTES OF A REGULAR MEETING OF THE

BINGHAMTON-JOHNSON CITY JOINT SEWAGE BOARD

Tuesday, December 12, 2006

Village of Johnson City, 2nd Floor Conference Room

 

Members Present: Thomas R. Augostini, Chairman

                                    Eugene Hulbert, Vice Chairman

Thomas Dellapenna, Jr.

                                    Kenneth Kinsman

                                   

Also Present:          Kenneth Helisek, Esq., Co-Counsel

Robert C. Murphy, Esq., Co-Counsel

                                    John Perticone, Esq., Co-Counsel

                                Catherine P. Aingworth, Interim Superintendent

                                    Beverly J. Palmer, Fiscal Officer - ABSENT

                                    John Cox, Fiscal Officer - ABSENT

            Michele Cuevas, Confidential Secretary

            Kathleen C. Carney, Transcriptionist

 

Guests:         Bob Bennett, Engineer, Village of Johnson City

John LaGorga, Stearns & Wheler

Howard LaFever, Stearns & Wheler

Arthur Van Gelder, C&S Engineers

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

 

Chairman Tom Augostini called the meeting to order at 1:31 p.m.  

 

PRIVILEGE OF THE FLOOR

 

Stearns & Wheler – John LaGorga

 

Lime Stabilization

 

John LaGorga reported that the lime stabilization silo has been installed.   The interior of the centrifuge room and the truck bay remain to be completed.  Due to a natural gas leak in the truck bay, the floor was torn up and has been repaired and new concrete poured.  The motor problems that were delaying the start up of the centrifuges have been resolved.  The centrifuges are being performance tested; the acceptance tests have not been performed yet.  The acceptance test is a six‑hour continuous test, it is contingent upon the ability to have continuous sludge flow.  The interior construction work has been delayed until January 2, 2007. 

 

Pre-Treatment Program

 

Stearns & Wheler has completed the annual sampling for the industries.  There are two outstanding issues, one concerns work being done at Frito Lay where the sanitary system is being impacted by infiltration and inflow and is backing up into the Frito Lay treatment process.  (The back up is in the Kirkwood system).   Michele Cuevas explained that there was a letter in Board members' packets from Stearns & Wheler that explains this situation in greater detail. 

 

Interim Superintendent Aingworth explained that she is requesting prints for all areas served so Plant management can have an idea of where flows are coming from. 

 

Mr. Hulbert explained that as the Plant's engineer (Stearns & Wheler) addressed a report indicating there may be problems with the Kirkwood system and its effect on the Frito Lay flow into the system, this becomes the Plant's problem.  He feels that the Town of Kirkwood should be contacted and asked to fix the problem. 

 

Chairman Augostini felt the Plant Management or Board should make a request to the Town of Kirkwood to fix the problem. He explained that the DEC faults our system, as we have no enforcement over the collection system. 

 

Mr. LaGorga advised approaching the issue from the Board explaining that Frito Lay has no bypass in the treatment process, which affects the Plant's treatment.  It can also be addressed from the City of Binghamton indicating that the excessive flows are affecting the system. 

 

Chairman Augostini asked Mr. LaGorga to draft a letter to Frito Lay, copying the DEC, for Interim Superintendent Aingworth's signature, expressing the Plant/Board's concern with this situation. 

 

Stearns & Wheler proposed conducting an energy audit at the Plant.  The proposal for the energy audit is not prepared at this point.  The first step in this proposal process would be to meet with NYSERDA on site.   They would then conduct a planning meeting in January at the treatment plant.  He indicated that Interim Superintendent Aingworth and a Board representative should be present at that meeting.  From that meeting, they will highlight areas of potential energy savings and present a proposal to the Board.

 

Stearns & Wheler provided the Board with a proposal for additional services related to the Pre-Treatment Program.  The proposal would include preparing a status of the current Pre-Treatment Program, comparing it with the minimum requirements by law and also comparing it with a benchmark/role model site.  It would also include assisting the Board in modifying the rules and regulations relating to the use of the treatment Plant, changing the local limits, adding hospitals and dental offices to the Pre-Treatment Program, developing a waste hauling program and establishing standards for fats, oils and grease (FOG). 

 

Chairman Augostini asked for time for the Board to review the proposal. 

 

Chairman Augostini asked for an update on Wilson Electroplaters.  The owner of Wilson Electroplaters has died.  Stearns & Wheler has sent a letter to the owner's daughter, (who is helping run the business), indicating they will contact her in one month's time to discuss correcting the situation.  Michele Cuevas indicated that the daughter has contacted the Plant and is more than willing to sit down and work on a remedy.

 

Michele Cuevas requested water usage information for the Hall Street (alternative fuels) business.  The amount of water usage has increased to a household of between 5 and 8 people during the past six months.   Interim Superintendent Aingworth received information from Kevin Transue that the alternative fuels facility has not started operations. 

 

C&S Engineers

 

Construction Progress

 

Mr. Van Gelder provided an update on the current contracts:

 

Contract 1 has been receiving the damaged parts from the June 2006 flooding.  IDI is working with Faulter (contract 3A) and Matco (contract 3B) to get those parts removed and reinstalled.  They will be discussing with Bob Bennett conducting multiple contract closures at once on the smaller contracts.  They will be looking at multiple warranty/guarantee periods due to the June floods.

 

Pumps: 

 

TPS:   Pumps are being expedited for TPS as the size of the pumps are smaller and the cost is about $3,000-$4,000 to expedite.  TPS will have two pumps delivered January 24, 2007 and two pumps delivered February 27, 2007.  The contractors are making arrangements and those agreements will be finalized in the near future. 

 

Headhouse:  It is not economically feasible to expedite two headhouse pumps as is being done for TPS.  The cost is $15,000 per pump at the headhouse and expediting them would only gain three weeks.  As it stands right now, the headhouse pumps will be on site by late February or mid-March. 

 

 

Much of the restoration is done.  Finishing work, striping, windows and doors are being installed. 

 

Contract 4:  There has been small delay in the boilers.  The boilers for the digester complex are expected by the middle of January.  

 

The engineers have asked Mr. Van Gelder to discuss the Hazard Mitigation Plan.  The Plan will be completed by the end of this week and will be ready for review and submittal to FEMA. 

 

SEMO for Contract 1 is completed and is being used to write the PWs for Contract 1. 

 

A letter was drafted to Bob Bennett on November 29 regarding the consent orders.  That letter was sent to Steve Eidt and Sandy Lizlovs. 

 

Centrifuge training is being conducted and is progressing well. 

 

Mr. Hulbert asked about the status of the baffles.  Mr. Van Gelder responded that baffle design is in final review by Bob Palladine.  The design is complete and the paperwork is ready to go out pending Bob's final review.   All 10 tanks have been inspected. 

 

Chairman Augostini will ask Bob Palladine for a status and schedule for the baffle installation.

 

Chairman Augostini informed the Board that he reviewed Broome County's Hazard Mitigation Plan and did not see anything about a floodwall for Lourdes Hospital.  He spoke to Frank Evangelisti of the county.  The hazard mitigation draft does not include recommendations for a floodwall or similar structures at Lourdes.  Although it has been discussed, it will not likely include a specific recommendation for a floodwall at Lourdes, but instead something like "design and implement a flood control system that is protective of Lourdes Hospital."  Mr. Evangelisti indicated that if the Joint Sewage Board was concerned about this, they should draft a letter to him so those concerns could be incorporated into a final plan.  

 

APPROVAL OF MINUTES

 

As there was not a quorum at the November 14, 2006 meeting, no formal business was conducted.

 

FISCAL OFFICER'S REPORT

 

Chairman Augostini presented a Fiscal Officer's report, dated December 12, 2006, with a balance of $2,703,425.51.    Receipts to date have equaled $8,277,832.83 with expenditures of $5,574,407.32.  All fourth quarter 2006 billings have been mailed and paid.  The first quarter 2007 bills will be mailed next week. 

 

Mr. Kinsman made a motion to accept the Fiscal Officer's report as presented.  Second by Mr. Hulbert. 

 

Motion carried:       4ayes

0 nay

2 vacancies 

 

BOARD LISTING

 

Chairman Augostini presented a Board listing of $231,307.59. 

 

Chairman Augostini asked Michele Cuevas to break out all flood data from the board listings.  Michele indicated that the flood issues are listed at the end of the Board Listing. 

Interim Superintendent Aingworth reported that the flood cleanup and emergency repairs are coming to an end.  She estimated that a rough estimate for flood cleanup and emergency repairs is $680,000.00. 

 

Mr. Dellapenna made a motion to approve and pay the Board Listing totaling $231,307.59.   Second by Mr. Kinsman.

 

Motion carried:       4 ayes

0 nay

2 vacancies 

 

It was agreed that for the future the Board Listing would be presented in a sorted list.

 

CORRESPONDENCE

 

Interim Superintendent Aingworth noted routine Pre-Treatment Program letters. 

 

Stearns & Wheler drafted a letter on behalf of Interim Superintendent Aingworth to Binghamton University which made mention of the plan to have a more aggressive FOG program and asked for their cooperation.  Interim Superintendent Aingworth indicated they would like to incorporate that with other Pre-Treatment users and restaurants.

 

Interim Superintendent Aingworth indicated a letter notifying the Plant that Monadnock is shutting down operations.  They were a problem from a BOD and TSS standpoint.

 

SUPERINTENDENT'S REPORT

 

Violations, Complaints & Significant Problems

                                   

·        Urgent repairs to the Johnson City Pump Station and Binghamton Main Pumps are pending.  Johnson City Pump Station has severe damage to pumps, shafts and inline channel grinders.  Pump #2 is nonfunctional.  The Binghamton main pump #1 is also currently nonfunctional.  Equipment has been ordered and we are awaiting their delivery. 

·        FEMA is awaiting project work sheet authorization.  Interim Superintendent Aingworth will contact co-counsel once she receives the draft from Mr. Palladine.  She would like to sign the work sheet authorization next week.  

·        There continues to be a controlled burn in the compost bioreactor.  Plant personnel monitor temperatures daily and apply nitrogen to control the temperature of the fire. Interim Superintendent Aingworth is meeting with the insurance agent on Friday regarding the compost facility. 

 

Compliance

 

·           The effluent suspended solids, BOD and iron limits were met in November.

·           Influent suspended solids were 118, and effluent suspended solids were 33, which is an average 75% removal.  Current effluent limits for suspended solids are 53.  Influent BOD was 122 and effluent BOD was 73, which is an average 40% removal.  The effluent BOD limit is 132.

 

Personnel

 

·           Pending:  Informational request from Civil Service regarding title changes. 

·           Continuing: Management personnel continue meeting with consultant Jack Bills

·           Continuing:  Labor Management meetings to discuss new management initiatives, including scheduling and training.

·           New:  Guidance policy for employee educational reimbursement.

·           New:  Flex schedules (12 hour shifts) for operators and shift supervisors are being considered.

·           Board policy regarding residency clarification is requested.

The Board discussed the residency requirements for employees. 

Co-counsel(s) Helisek and Perticone reviewed the agreement and determined that any new employees must be a resident of either party (Johnson City or Binghamton).  There is no way of knowing whether there has previously been a resolution amending this requirement.  Co-counsel Helisek advised that the only way to change this requirement is to amend the Inter-Municipal Agreement.  In order for someone to be hired by the Plant at this time they must be a resident of Binghamton or Johnson City.

 

Co-counsel Helisek recommended that Johnson City submit a proposal to the City of Binghamton asking what portions of the Inter-Municipal Agreement should be amended now as well as indicating what portions Johnson City would like amended.  It is agreed that the entire agreement should be changed, but do not have time now to amend the entire agreement. 

 

It was decided that Chairman Augostini would ask Mayor Lewis to frame the issues that Johnson City would like to see modified.  He will send them to Binghamton; Binghamton can frame their issues and the two municipalities can then compare the issues and make the necessary changes.

 

Compost Facility

 

·        Continuing:  The compost bioreactor continues a controlled burn. 

 

Operational Issues

 

·           Ten out of ten settling tanks are on line.

·           Request collection system prints from areas we serve.  We had sets that were damaged in the flood.  Interim Superintendent Aingworth will make this request.

·           Emergency repairs to the gas line because of a gas leak in the filter building needed to be made the last week of November. 

 

Digesters

 

·              Number 3 digester is currently working to stabilize solids. 

 

Centrifuges

 

·              The Westphalia centrifuge is on-line. 

·              We are working with Westphalia to start up the two new additional centrifuges. 

·              Work for the lime upgrade equipment has begun.

 

Influent Pumps

 

·              Pending:  Corrective action is being planned through C & S Engineers and lead agency, the Village of Johnson City.  The Johnson City Terminal Pump Station suffered significant damage.  The corrective action being coordinated by Johnson City may assist in the repair of some problems. 

   

 Primary Tanks

 

·           We are in chemical precipitation and primary settling only mode with tanks 1-10 on line. 

 

Industrial Pretreatment Program

 

·        Continuing:  Stearns & Wheler is assisting our staff with the Industrial Pretreatment Program. 

·        Monadnock (*formerly known as Landers) has ceased production and moved their facility to New Hampshire.

 

Plant Business

 

·           The Plant Interim Superintendent has been invited to give a presentation at the New York Water Environment meeting in February 2007 regarding our experiences with the June 2006 flood.

·           The Plant has been contacted by Stearns & Wheler regarding the County study of wastewater treatment plants and capacity.

·           Plant personnel are soliciting information and quotes pertaining to safety programs and equipment.

 

Recommended Board Actions

 

·           Consider a website for the Plant.

·           Request permission for Catherine Aingworth to attend the February NYWEA meeting in New York City.

·           Request prints of collection systems from the municipalities we serve. 

·           Recommendation regarding FEMA project worksheets. 

 

Contract 3 – BAF's

 

·           Work is in progress.

·           Jack Gaasch, the New York Grade 4 operator consultant for IDI has made site visits to the Plant and we are beginning to coordinate the start up plan for the BAFs with him.

·           Plant personnel have had meetings with IDI and C&S regarding start up plans.

 

Contract 4 – Solids Handling

 

Work is in progress.

 

Motion made by Mr. Kinsman granting permission for Interim Superintendent Aingworth to attend the NYWEA Conference in New York City from February 5 through February 7, 2007.  All customary and reasonable expenses will be reimbursed.   Second by Mr. Hulbert.

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

Interim Superintendent Aingworth reviewed with the Board the union agreement for the Building Maintenance Helper.  She explained there was some confusion regarding what the starting and base salary would be for this position.   The newly accepted union agreement will supercede the November 18, 2006 agreement. 

 

BOARD COMMITTEE REPORTS

 

The Personnel Committee worked developing the new union contract.

 

OLD BUSINESS

 

There was no old business.

 

NEW BUSINESS

 

Chairman Augostini invited the Board to the Plant Holiday Party to be held at Red's Kettle Inn on Saturday, December 16, 2006 from 1:00 p.m. to 6:00 p.m.

 

Interim Superintendent Aingworth asked that consideration be given again for a website for the Plant.  Chairman Augostini asked Interim Superintendent Aingworth to contact Donna McCue of McCue Advertising (who had previously provided information regarding public relations/website development) and ask her to attend a future meeting.

 

Chairman Augostini asked for nominations for Vice Chairman for 2007.  (Mr. Hulbert is Chairman for the 2007 year). 

 

Motion by Mr. Dellapenna to nominate Mr. Kinsman as Vice Chairman for the Joint Sewage Board for 2007.  Second by Mr. Hulbert. 

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

 

EXECUTIVE SESSION

 

Motion by Mr. Kinsman to enter Executive Session at 2:55 p.m. to discuss the collective bargaining agreement and personnel matters.  Second by Mr. Dellapenna.

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

Motion by Mr. Kinsman to exit Executive Session at 3:25 p.m.  Second by Mr. Hulbert.

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

Chairman Augostini asked for a motion to ratify the tentative union contract between the Joint Sewage Board and CSEA through December 31, 2008 subject to approval by legal counsel as explained by Mr. Richardson and Mr. Murphy.

 

Motion by Mr. Kinsman to ratify the tentative union contract between the Joint Sewage Board and CSEA through December 31, 2008 subject to approval by legal counsel as explained by Mr. Richardson and Attorney Murphy.  Second by Mr. Hulbert.

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

A resolution must be made adopting 41J.  Chairman Augostini will have that information available for the January 2007 meeting. 

 

Mr. Hulbert thanked Mr. Richardson, Attorney Murphy, Mr. Abbott and the personnel committee for their work ratifying the union contact.

 

Chairman Augostini will forward the new agreement to all Board members. 

 

Chairman Augostini noted that co-counsel J. Perticone is on vacation from December 18, 2006 until January 3, 2007.  Co-counsel K. Helisek is on vacation beginning December 24, 2006. 

 

ADJOURNMENT

 

Motion by Mr. Dellapenna to adjourn at 4:55 p.m.  Second by Mr. Kinsman

 

Motion carried:       4 ayes

0 nay

2 vacancies

 

The next regularly scheduled meeting is scheduled for Tuesday, January 9, 2007 at 1:30 p.m. in the City Clerk's Conference Room at the City of Binghamton.

 

TIME & PLACE OF NEXT BOARD MEETINGS

 

Tuesday, January 9, 2007 @ 1:30 PM

City Clerk's Conference Room, City of Binghamton

 

Respectfully submitted,

 

Kathleen C. Carney

Transcriptionist

cc:       All Board Members

            Mayor Ryan, City of Binghamton

            Mayor Lewis, Village of Johnson City

            Kenneth P. Helisek, Esq.

            Robert C. Murphy, Esq.

            John L. Perticone, Esq.

            Beverly J. Palmer, Fiscal Officer

            John Cox, Deputy Comptroller

            Catherine Aingworth, Acting Superintendent

            City of Binghamton, City Clerk

Haylor, Freyer & Coon

File